Will You Add?
#1 in Business Subscribe Email Print

You are here: Home > Business > Management > Increasing Project Value through Risk Management

Tags

  • uncertainty
  • budgeted
  • evaluated against
  • addressing project
  • dollar store

  • Links

  • Whole Bean Coffee - A Complete Review
  • Incorporating Plant Stands and Indoor Planters in Your Home Decor
  • Keeping Employees For The Long Run- Employee Retention
  • Will You Add? - Increasing Project Value through Risk Management

    How to Improve Your Work Situation
    buWhy are so many people unhappy in their work situation? Why do people, who are successful at one career, have such difficult times coping with their new career? These problems frequently occur, because conflicts exist in their work relationships.Relationships between you and your work can also be considered the "games of work." Games have basic rules to play, which require specific skills to succeed at playing. People win at the games they play when they achieve the game objectives and by operating within the rules of the game better than others. The "games of work" also have objectives and basic rules that must be followed to succeed.There are many different sports games and the
    rements could be tightened by first developing a proof-of-concept or simply by delaying the project until the uncertainties can be eliminated. By taking this approach, the value of the project can be increased by eliminating the $5,000 reduction for the risk of uncertainty.

    2. A proof-of-concept could also be evaluated by the sales force to ensure that they will not need training, as feared, thereby eliminating the second risk and increasing the project's value by an additional $2,000.

    3. Finally, although external uncertainties cannot be eliminated, mitigation and contingency plans can be put in place to reduce the overall impact on the project's value. For example, instead of structuring the project as an all-or-nothing proposition, perhaps it can be implemented so that parts or stages of it can be adapted to many different environments. Perhaps the data structu

    Online Billing: Save a Call
    If you are looking to save money then look no further than electronic billing or online billing--sometimes referred to as EBPP. National averages per call received in a call center or by a customer service rep can be as much as $5.00. Reduce this by 50% and you save a significant sum of money. The question is how to reduce the number of calls flowing to your call center? The answer: short and sweet, electronic billing or online billing.National statistics show that 60% of all calls to a call center are billing related. Questions such as, "Can you send me another copy of the bill?" "Why did my bill increase?" "I didn't get my bill" can send your customer service reps over the edge; however, when you use an elec
    Most organizations have more project proposals and ideas than they can realistically fund. This means project teams are competing for project approval and funding. Consequently, project champions often conceal or exaggerate the true value of their projects. Teams and organizations typically focus on the up-front costs of a project and the expected return. Other costs are glossed over or ignored entirely, and risk assessment is treated as a perfunctory afterthought. This focus on the up-front costs and the net return is only half of the story, however.

    It may be time to stop thinking of risk assessment as the killjoy exercise which drains the enthusiasm from your project and to start thinking of it as a tool for enhancing your project's value.

    Understanding the Fundamentals:

    A project risk is any problem that could cause some loss or threaten the success of the project1. Risks differ from issues because they refer to the future or to the potential for adverse outcome.

    “A risk consists of a condition which is not currently true, the likelihood that the condition will materialize, and a consequence or impact on the project if the condition does materialize.”

    Risk management is the process of identifying, analyzing, and addressing project risks proactively to maximize positive consequences (opportunities) and minimize negative consequences (losses). Risks are addressed by formulating mitigation plans, which are aimed at reducing the likelihood that the condition will materialize, and contingency plans, which are aimed at addressing the condition when it does materialize.

    As mentioned above, the value of a project is determined by its net return and its risks. The net return on the project is equal to the present value of the project minus the costs (return = present value - costs). This return assumes that the project will proceed as planned and budgeted - that is, it assumes a risk-free project. But projects are rarely risk-free. To get a true assessment of the project, the return must be evaluated against the risks.

    Applying Risk Management:

    Suppose I have a project proposal to unify two corporate databases. I estimate that this will save the organization $100,000 over five years and that it will cost $80,000 to implement. The return is $20,000 without factoring in any risks, but there are risks.

    1. Due to some uncertainty in the requirements, there is a 50% likelihood that the development effort will cost an additional $10,000. This comes to a reduction of the return by $5,000 ($10,000 x .50).

    2. Although the project team has assurance from sales that the impact upon the sales force will not be substantial, the team believes that there is still a 25% likelihood that upon seeing the changes, sales will require additional training, costing $8,000, thereby reducing the return by $2,000 ($8,000 x 25).

    3. Due to some inherent uncertainties regarding the technologies, as well as the direction of the organization and some anticipated acquisitions, there is a 10% likelihood that the entire project will fail or be superseded by other efforts. This means a reduction of the return by $8,000 ($80,000 in overall project costs x .10).

    When all risks are factored, the reduction on the return is $5,000 + $2,000 + $8,000 or $15,000. The return is now $20,000 - $15,000 or $5,000, making the project substantially less attractive than it originally appeared. But by managing the risks, the value of this project can be increased to a level that again makes it attractive.

    1. First, the requirements could be tightened by first developing a proof-of-concept or simply by delaying the project until the uncertainties can be eliminated. By taking this approach, the value of the project can be increased by eliminating the $5,000 reduction for the risk of uncertainty.

    2. A proof-of-concept could also be evaluated by the sales force to ensure that they will not need training, as feared, thereby eliminating the second risk and increasing the project's value by an additional $2,000.

    3. Finally, although external uncertainties cannot be eliminated, mitigation and contingency plans can be put in place to reduce the overall impact on the project's value. For example, instead of structuring the project as an all-or-nothing proposition, perhaps it can be implemented so that parts or stages of it can be adapted to many different environments. Perhaps the data structu

    4 Alternative Ways To Gain Lifetime Customers
    You will always have more people that turn down your offer than actually buy. They might not have bought because of your price, payment options, or any other possible reason. You will just end up loosing all these potential lifetime customers. However, there are many ways you can minimize the loss of these prospects.One way is to accept barter offers for your product. Maybe the person can't afford to buy your product. They may have something you could use in your business or personal life. If the barter deal isn't fair enough, either of you could add in some cash. You may not make money but, they might buy other products you offer.Another way is to include a negotiation offer at the end of
    sks differ from issues because they refer to the future or to the potential for adverse outcome.

    “A risk consists of a condition which is not currently true, the likelihood that the condition will materialize, and a consequence or impact on the project if the condition does materialize.”

    Risk management is the process of identifying, analyzing, and addressing project risks proactively to maximize positive consequences (opportunities) and minimize negative consequences (losses). Risks are addressed by formulating mitigation plans, which are aimed at reducing the likelihood that the condition will materialize, and contingency plans, which are aimed at addressing the condition when it does materialize.

    As mentioned above, the value of a project is determined by its net return and its risks. The net return on the project is equal to the present value of the project minus the costs (return = present value - costs). This return assumes that the project will proceed as planned and budgeted - that is, it assumes a risk-free project. But projects are rarely risk-free. To get a true assessment of the project, the return must be evaluated against the risks.

    Applying Risk Management:

    Suppose I have a project proposal to unify two corporate databases. I estimate that this will save the organization $100,000 over five years and that it will cost $80,000 to implement. The return is $20,000 without factoring in any risks, but there are risks.

    1. Due to some uncertainty in the requirements, there is a 50% likelihood that the development effort will cost an additional $10,000. This comes to a reduction of the return by $5,000 ($10,000 x .50).

    2. Although the project team has assurance from sales that the impact upon the sales force will not be substantial, the team believes that there is still a 25% likelihood that upon seeing the changes, sales will require additional training, costing $8,000, thereby reducing the return by $2,000 ($8,000 x 25).

    3. Due to some inherent uncertainties regarding the technologies, as well as the direction of the organization and some anticipated acquisitions, there is a 10% likelihood that the entire project will fail or be superseded by other efforts. This means a reduction of the return by $8,000 ($80,000 in overall project costs x .10).

    When all risks are factored, the reduction on the return is $5,000 + $2,000 + $8,000 or $15,000. The return is now $20,000 - $15,000 or $5,000, making the project substantially less attractive than it originally appeared. But by managing the risks, the value of this project can be increased to a level that again makes it attractive.

    1. First, the requirements could be tightened by first developing a proof-of-concept or simply by delaying the project until the uncertainties can be eliminated. By taking this approach, the value of the project can be increased by eliminating the $5,000 reduction for the risk of uncertainty.

    2. A proof-of-concept could also be evaluated by the sales force to ensure that they will not need training, as feared, thereby eliminating the second risk and increasing the project's value by an additional $2,000.

    3. Finally, although external uncertainties cannot be eliminated, mitigation and contingency plans can be put in place to reduce the overall impact on the project's value. For example, instead of structuring the project as an all-or-nothing proposition, perhaps it can be implemented so that parts or stages of it can be adapted to many different environments. Perhaps the data structu

    Branding a Small Business Without Paying A Dime
    As a young entrepreneur I was always looking for ways to brand my small companies. I didn't want to hire a firm and I was always open to learning. These are some things I've learned along the way that you might find helpful.My top 5 ways of building a brand for your small business - without paying a dime.Build a Website A website is something that almost any small business owner can build and maintain on his/her own without too much difficulty. There are a dozen or more free services out there that will not only give you free hosting but help you build a website as well.Market Your Website Using free directories and forums, begin to grow your web presence so that
    e costs (return = present value - costs). This return assumes that the project will proceed as planned and budgeted - that is, it assumes a risk-free project. But projects are rarely risk-free. To get a true assessment of the project, the return must be evaluated against the risks.

    Applying Risk Management:

    Suppose I have a project proposal to unify two corporate databases. I estimate that this will save the organization $100,000 over five years and that it will cost $80,000 to implement. The return is $20,000 without factoring in any risks, but there are risks.

    1. Due to some uncertainty in the requirements, there is a 50% likelihood that the development effort will cost an additional $10,000. This comes to a reduction of the return by $5,000 ($10,000 x .50).

    2. Although the project team has assurance from sales that the impact upon the sales force will not be substantial, the team believes that there is still a 25% likelihood that upon seeing the changes, sales will require additional training, costing $8,000, thereby reducing the return by $2,000 ($8,000 x 25).

    3. Due to some inherent uncertainties regarding the technologies, as well as the direction of the organization and some anticipated acquisitions, there is a 10% likelihood that the entire project will fail or be superseded by other efforts. This means a reduction of the return by $8,000 ($80,000 in overall project costs x .10).

    When all risks are factored, the reduction on the return is $5,000 + $2,000 + $8,000 or $15,000. The return is now $20,000 - $15,000 or $5,000, making the project substantially less attractive than it originally appeared. But by managing the risks, the value of this project can be increased to a level that again makes it attractive.

    1. First, the requirements could be tightened by first developing a proof-of-concept or simply by delaying the project until the uncertainties can be eliminated. By taking this approach, the value of the project can be increased by eliminating the $5,000 reduction for the risk of uncertainty.

    2. A proof-of-concept could also be evaluated by the sales force to ensure that they will not need training, as feared, thereby eliminating the second risk and increasing the project's value by an additional $2,000.

    3. Finally, although external uncertainties cannot be eliminated, mitigation and contingency plans can be put in place to reduce the overall impact on the project's value. For example, instead of structuring the project as an all-or-nothing proposition, perhaps it can be implemented so that parts or stages of it can be adapted to many different environments. Perhaps the data structu

    Opening a Dollar Store - Let Potential Customers Know You are There!
    One of the biggest challenges faced when opening a dollar store is getting the word out that you are there and that your store is open for business. The better job you do at getting this vital information out to potential shoppers the more quickly you will be moving toward success. The more potential shoppers that you can bring into your store the more likely you are to make money in retailing.Many who are considering opening a dollar store immediately assume that it will cost huge sums of money to get the word out. Yet there are many no-cost and low-cost actions that you can take to initially get potential shopper attention. Take the time to develop your plan before your store opens for business.Start
    ntial, the team believes that there is still a 25% likelihood that upon seeing the changes, sales will require additional training, costing $8,000, thereby reducing the return by $2,000 ($8,000 x 25).

    3. Due to some inherent uncertainties regarding the technologies, as well as the direction of the organization and some anticipated acquisitions, there is a 10% likelihood that the entire project will fail or be superseded by other efforts. This means a reduction of the return by $8,000 ($80,000 in overall project costs x .10).

    When all risks are factored, the reduction on the return is $5,000 + $2,000 + $8,000 or $15,000. The return is now $20,000 - $15,000 or $5,000, making the project substantially less attractive than it originally appeared. But by managing the risks, the value of this project can be increased to a level that again makes it attractive.

    1. First, the requirements could be tightened by first developing a proof-of-concept or simply by delaying the project until the uncertainties can be eliminated. By taking this approach, the value of the project can be increased by eliminating the $5,000 reduction for the risk of uncertainty.

    2. A proof-of-concept could also be evaluated by the sales force to ensure that they will not need training, as feared, thereby eliminating the second risk and increasing the project's value by an additional $2,000.

    3. Finally, although external uncertainties cannot be eliminated, mitigation and contingency plans can be put in place to reduce the overall impact on the project's value. For example, instead of structuring the project as an all-or-nothing proposition, perhaps it can be implemented so that parts or stages of it can be adapted to many different environments. Perhaps the data structu

    Costa Rica - New Hi-Tech Free Zone
    NEW FREE ZONE FOCUSES ON SERVICES. The Zeta Group has inaugurated construction of a free zone in Cartago, reports The Tico Times (June 1-7, 2007). It joins two large free zones announced in the past two months by Free Zone & Business Park Developer (FZBP). The projects highlight the continuing move away from manufacturing in favor of service, vending, and administrative businesses. Some 57% of businesses in Costa Rica's 23 free zones are dedicated to manufacturing, but Timothy Scott, Exec. Dir. of the Costa Rican Association of Free-Zone Businesses (AZOFRAS), says that is changing, partly due to a World Trade Organization (WTO) decision in 2001 against government incentives granted to export manufacturers:Zet
    rements could be tightened by first developing a proof-of-concept or simply by delaying the project until the uncertainties can be eliminated. By taking this approach, the value of the project can be increased by eliminating the $5,000 reduction for the risk of uncertainty.

    2. A proof-of-concept could also be evaluated by the sales force to ensure that they will not need training, as feared, thereby eliminating the second risk and increasing the project's value by an additional $2,000.

    3. Finally, although external uncertainties cannot be eliminated, mitigation and contingency plans can be put in place to reduce the overall impact on the project's value. For example, instead of structuring the project as an all-or-nothing proposition, perhaps it can be implemented so that parts or stages of it can be adapted to many different environments. Perhaps the data structures and encoding can be separated from the database implementation so that if organizational changes arise that undermine the implementation, the data structures can still be used in the implementation ultimately adopted by the organization. If a third of the work can be salvaged, the value of the project is increased by $2,640 ($8,000 x .33).

    This brings the total increase in return as a result of risk management to $9,640.

    After risk management, the value of the project is $14,640 ($5,000 return after risk assessment + total increase in return after risk management).

    Conclusion:

    The true value of a project cannot be evaluated without being realistic about the costs of the undertaking, including the risks. Risks that are simply acknowledged and built into the costs will always lessen the value of a project, motivating project managers to report overly optimistic outlooks, which undermines the very reason for considering risks. But if risks are actively managed by meeting them head-on, formulating mitigation and contingency plans and treating risk management as an ongoing process, risks can be minimized. As a result, project values can be increased, and organizations will get a more accurate and consistent understanding of project values.

    HTTP = HTML link (for blogs, profiles,phorums):
    <a href="http://www.atriclecheck.com/article/22632/atriclecheck-Increasing-Project-Value-through-Risk-Management.html">Increasing Project Value through Risk Management</a>

    BB link (for phorums):
    [url=http://www.atriclecheck.com/article/22632/atriclecheck-Increasing-Project-Value-through-Risk-Management.html]Increasing Project Value through Risk Management[/url]

    Related Articles:

    Medical Coding Careers

    To Be Distinctive, Be Different

    How Well is Your Board Performing?

    Bookmark it: del.icio.us digg.com reddit.com netvouz.com google.com yahoo.com technorati.com furl.net bloglines.com socialdust.com ma.gnolia.com newsvine.com slashdot.org simpy.com shadows.com blinklist.com